H3 building of Wrocław University of Technology at 41 Wyspiańskiego Street in Wrocław Implemented in: 01.12.2004 – 28.10.2005 |
more>>
Investor: Wrocław University of Technology, ul. Wybrzeże Wyspiańskiego 27, 50 – 370 Wrocław
The project implemented by Budopol – Wrocław consisted in the extension of the existing H-3 building of Wrocław University of Technology. The building was enlarged by over 1200 square meters (before the extension, the surface area totalled 825 square meters). The building will be used primarily as a scientific and teaching centre by the Faculty of Civil Engineering, focusing on research in the area of construction of bridges, railways, roads, and underground municipal infrastructure. The building also houses offices of the research, teaching, and administration staff, as well as welfare facilities, storage areas and technical facilities. The building was classified as an educational facility to be used for laboratories, classrooms, and offices. The project included: 1. extension of the laboratory and research building by adding a slab-on-grade laboratory hall with the total footprint of 155 square meters; 2. vertical extension of the existing building by adding one storey to be used for offices and classrooms, with the total footprint of 767 square meters; 3. refurbishment of the existing building to the extent necessary to enlarge the building and join architectural elements of the elevation. The project was implemented in two stages. Phase 1: construction of the new part including a laboratory hall and office rooms, as well as technical infrastructure. Phase 2: Construction of an additional storey and refurbishment of the existing building. The existing surfaces of access roads and inner yards, as well as fencing on the street side, were also upgraded. The building was fitted with all sanitary and electrical systems, including air conditioning and specialist security systems.
|
Laboratory of the Faculty of Electronics of Wrocław University of Technology at 65a Długa Street in Wrocław Implemented in: 09.06.2003 – 15.09.2003 |
more>>
Modernisation and adaptation works, including construction, sanitary, and electrical works in the Semiconductor Equipment Laboratory and offices of the Institute of Microsystems of the Faculty of Electronics at Wrocław University of Technology, 65a Długa Street in Wrocław.
Investor: Wrocław University of Technology, Investments and Repairs Department, ul. Wybrzeże Wyspiańskiego 27, 50-370 Wrocław.
The project implemented by Budopol – Wrocław S.A. consisted in the adaptation of the existing complex of three combined single-aisle warehouses without water supply and sewerage systems into a laboratory and offices, classrooms, and technical rooms with high-quality finishing. The existing building consisting of three cuboid-shaped units joined by endwalls, covered by a symmetric pitched roof, was modified by shifting the middle module vs. the remaining two modules by 50%, and segment 1 was moved upwards vs. the remaining segments by adding one storey for office rooms. A reinforced-concrete ramp for the unloading of delivery vehicles was constructed. The building was equipped with electrical service connections, sanitary system, internal logistics and telecommunications network, and some rooms were fitted with air conditioning. As certain rooms are used as laboratories (class 10,000 clean rooms), the highest degree of care was needed when installing partition walls, suspended ceilings, and doors with air showers.
|
Extension and modernisation of the lower secondary school no. 24 in Wrocław, including sport facilities and a public & school library Implemented in: 20.11.2001 – 30.06.2003 |
more>>
Investor: Zarząd Inwestycji Miejskich (Municipal Investments Board), ul. Januszowicka 15a, acting for and on behalf of the Municipality of Wrocław
Total gross value: PLN 5,100,292.29 + PLN 97,788.54 (additional works)
Tasks implemented: demolition of floors, stairs, columns, walls, floor toppings, and joinery, building construction and finishing works, sanitary and electrical works, and area improvements (including sport facilities). The task “Extension and modernisation of lower secondary school no. 24 (for 400 students) in Wrocław implemented by Budopol-Wrocław S.A.” consisted in the general overhaul of the existing 3-storey deep-basement building constructed in 1913 – 1915 using the traditional technologies, with a pitched roof covered with ceramic tiles, and construction of a new, slab-on-grade, 2-storey section with a design corresponding to the existing building, with a single-storey slab-on-grade sport section. After the extension, the entire building consists now of several sections with different heights, connected with pitched roofs covered with ceramic tiles. The front part of the plot is occupied by the existing building, connected with the public library and sport facilities with a link containing administration offices. In the middle part with a separate entrance from the north, there is a public library on the ground floor and classrooms on the 1st floor. The gym with welfare facilities and a separate entrance on the eastern endwall is located in the eastern part of the building. Further to the east, there is a multi-function sport field and a volleyball court, with a running track and long-jump pit to the north. The lift provides access for the disabled. The following connections and service lines were provided: water supply, sewerage, and rainwater drainage. The building was equipped in the following service systems: water and sewerage, gas and heat supply, mechanical ventilation, and new electrical systems (lighting, alarm and call, fire alarm, telephone, and burglar alarm). A modern gas-fired boiler room with weather compensation was also installed. Extension and modernisation of the school was performed in difficult conditions – the school was not closed. In phase 1, the new section was built along with the necessary infrastructure. Classes were held in the “old” building and then moved to the new section, and later modernisation works were performed in the existing building dating back to the beginning of the 20th century.
|
Building of the Faculty of Law and Administration of the University of Wrocław, 7 Uniwersytecka Street in Wrocław Implemented in: 25.04.2001 – 31.10.2002 |
more>>
Seat of the Faculty of Law and Administration of the University of Wrocław in the very centre of Wrocław along Uniwersytecka and Kuźnicza Streets, with wings adjoining the Old Town buildings. The building is L-shaped. The part located along Kuźnicza Street has 6 over-ground storeys and includes an entrance hall, cafeteria, classrooms, library, offices, and circulation routes. The second part at Uniwersytecka Street has two high storeys with lecture halls. The underground section of both parts includes car park areas and technical facilities. Vertical communication in the building includes two staircases, main stairs leading from the ground floor to the 2 nd floor, two passenger lifts and one goods and passenger lift. The building has all electrical and sanitary service connections, including mechanical ventilation and air conditioning, and is adapted for the disabled access, offering sufficiently wide circulation routes and entrances, lifts for vertical communication, and special facilities in toilets on all floors. The main entrance is at the pavement level with no stairs. The sophisticated facade of the building integrates well with the neighbouring historic buildings. The facade was made of modern glass of different degree of transparency combined with stone cladding. The project included: building construction and finishing works, sanitary and electrical works, area improvements, outdoor infrastructure, and acoustic protection.
|
Link between two buildings of the Faculty of Law and Administration of the University of Wrocław, 8-12 Więzienna Street in Wrocław Implemented in: 1999 - 2000 |
more>>
Investor: Zarząd Inwestycji Szkół Wyższych (University Investments Board), Wrocław, ul. Czerwonego Krzyża 2/4
On a plot of land located in Wrocław Old Town in the area protected by the Building Conservation Officer, Budopol – Wrocław implemented a project consisting in the construction of a link between buildings of the Faculty of Law of the University of Wrocław in the quarter 22/26 Uniwersytecka Street – 46 Kuźnicza Street – 8-12 Więzienna Street. The link is a 2-storey slab-on-grade building with a habitable attic. The link houses office rooms for the University staff, a corridor connecting the two parts of the Faculty of Law and Administration, reading room, classroom for 30 students, as well as auxiliary and technical facilities. To ensure good communication, a common staircase was built for all 3 storeys as well as stairs leading to the entrance, fitted with a lift for wheelchairs. High-quality materials were used in the finishing works. The plinth was covered with limestone up to the level of ground-floor windowsills. The scope of works included: demolition, construction and finishing, sanitary and electrical works, and area improvement.
|
Infill building of the Faculty of Law and Administration of the University of Wrocław, 8-12 Więzienna Street in Wrocław Implemented in: 12.1996 – 11.1998 |
more>>
Investor: University of Wrocław represented by the University Investments Board, Wrocław, ul. Czerwonego Krzyża 2/4
Floor space: 2539 square meters
Cubage: 12,869 cubic meters
Height: 5 storeys
Total value: 9,626.00 PLN
In the area at 8-12 Więzienna Street, on a plot of land of 1185 square meters located between two 4-storey historic classicist buildings, a 5-storey infill building with 80% basement and a pitched roof was built by Budopol – Wrocław. The main entrance with a passenger lift is located at Więzienna Street. The building has the second vertical evacuation route and an additional entrance from the inner yard. The gate for vehicles is leading to the inner yard. The new building of the Faculty of Law of the University of Wrocław includes library storage rooms in the basement, while the ground floor houses the main entrance hall with cloakrooms and a reception desk, and the reading room. The 1st and 2nd floor have one auditorium for 198 students and one lecture hall each. The 3rd floor houses a lecture hall and one classroom, while the attic has four classrooms, one office room, and two guest rooms with bathrooms. The following systems were installed in the building: central heating with a heat distribution substation, cold and hot water, fire protection, sewerage, mechanical ventilation, electrical service connections, and telephone lines. The project included: building construction and finishing, sanitary and electrical works, transfer of the heating network, protection of walls of neighbouring buildings, and area improvement.
|
Primary School No. 51 at Krępicka Street in Wrocław (Leśnica housing estate) Implemented in: 06.1997 – 07.1998 |
more>>
Investor: Dyrekcja Miejskich Inwestycji Komunalnych we Wrocławiu (Municipal Investments Directorate in Wrocław), ul. Powstańców Śl. 5, 53-332 Wrocław
Scope of works: phase 1 – building and installation works (school building and a boiler room, transformer station, land improvement, sport field with a running track, landscaping elements, building systems and networks).
Net value: PLN 6,003,385.00.